Delay notice
A delay notice is a formal communication issued by a contractor or subcontractor to notify the client (or sometimes the main contractor) of a delay that affects the progress of the construction works. This could be due to various reasons such as unforeseen site conditions, weather, supply chain issues and so on.This notice is a crucial part of project management and contractual compliance, as it informs the relevant parties about disruptions and helps manage expectations, mitigate risks, and assess potential impacts on project timelines and costs.
Many construction contracts, including standard forms like those from JCT (Joint Contracts Tribunal) or NEC (New Engineering Contract), include provisions that require contractors to issue a delay notice within a specified time frame once a delay is identified.
Proper documentation and record-keeping are critical. The delay notice should be well-documented, with all relevant evidence and supporting information to substantiate the claim of delay.
A typical delay notice might include:
- A detailed explanation of the cause and nature of the delay.
- The date the delay began and the estimated duration of the delay.
- Assessment of how the delay will affect the project’s timeline, milestones, and completion date.
- Steps being taken to mitigate the delay.
- Any requests for extensions of time (EOT) or additional resources.
Prompt issuance of a delay notice is essential. Contracts often specify a time limit within which the notice must be given after the contractor becomes aware of the delay. Failure to provide timely notice can affect the contractor's ability to claim an extension of time or additional costs.
The delay notice is typically the first step in the process of applying for an extension of time. If the delay is justified and beyond the contractor’s control, the contract administrator may grant an EOT, thereby adjusting the project schedule without imposing liquidated damages for late completion.
[edit] Related articles on Designing Buildings
- Acceleration.
- Compensation event.
- Concurrent delay.
- Contractor delay.
- Critical path.
- Culpable delay.
- Delay.
- Delay to completion.
- Delay to progress.
- Dispute resolution.
- Disruption claims in construction.
- Employer delay.
- Extension of time.
- International research into the causes of delays on construction projects.
- Liquidated damages.
- Long lead-time item.
- Programme.
- Relevant event.
- Relevant event v relevant matter.
- Relevant matter.
Featured articles and news
The act of preservation may sometimes be futile.
Twas the site before Christmas...
A rhyme for the industry and a thankyou to our supporters.
Plumbing and heating systems in schools
New apprentice pay rates coming into effect in the new year
Addressing the impact of recent national minimum wage changes.
EBSSA support for the new industry competence structure
The Engineering and Building Services Skills Authority, in working group 2.
Notes from BSRIA Sustainable Futures briefing
From carbon down to the all important customer: Redefining Retrofit for Net Zero Living.
Principal Designer: A New Opportunity for Architects
ACA launches a Principal Designer Register for architects.
A new government plan for housing and nature recovery
Exploring a new housing and infrastructure nature recovery framework.
Leveraging technology to enhance prospects for students
A case study on the significance of the Autodesk Revit certification.
Fundamental Review of Building Regulations Guidance
Announced during commons debate on the Grenfell Inquiry Phase 2 report.
CIAT responds to the updated National Planning Policy Framework
With key changes in the revised NPPF outlined.
Councils and communities highlighted for delivery of common-sense housing in planning overhaul
As government follows up with mandatory housing targets.